Kingston Fossil Plant  Scrubbers to be Commissioned
The Kingston Fossil Plant (KIF)  will start up to five units on June 14, 2010, that will tie onto the new  scrubber; the four remaining units will tie in at a later date.  The scrubber is  just one part of TVA’s overall air quality program that will lower sulfur  dioxide (SO2) emissions from burning coal by more than 95 percent.  The  scrubbers work by mixing limestone and water with flue gas.  The limestone  mixture converts the SO2 to gypsum which will be stored on site. You may see a  white plume that will rise from the scrubber--this is water vapor resulting from  the scrubbing process.   
Commissioning activities will  continue through the summer with various units to test and verify that the  scrubber operates properly at varying levels of power production.  All units  will be removed from service in September 2010 and will remain off unless needed  for system reliability.
Temporary Closure of Swan  Pond Circle Road
Swan Pond Circle Road near  Berkshire will close on June 16, 2010 for up to two days.  The final tie-in of  the bypass road, parallel to Swan Pond Circle Road, will be executed on these  two days.   During this time travelers will need to use the northern Swan Pond  Road intersection for access to Swan Pond Circle Road.  After the bypass road  has been completed and is ready for use, Swan Pond Circle Road will be closed  for construction of the underpass bridge.  Traffic will be diverted to the  bypass road until the construction of the bridge is complete.  When the bridge  is complete, Swan Pond Circle Road will be reopened and the bypass road will be  removed. 
Utility Restorations  Continue
Utility work will  begin at the intersection of Hassler Mill Road and Highland Drive early next  week and continue east toward Swan Pond Road.   One lane of Hassler Mill Road  will be closed in the work zones and flaggers will be in place to direct  traffic.   The work is expected to be complete in about three  weeks.
Also beginning next  week and continuing for about two weeks, utility work will begin at the  intersection of U.S. Highway 70 and Swan Pond Road.  While equipment is being  unloaded one lane of traffic will be closed.  Flaggers will be in place during  this time.  
Upper Bluff Road  Lease to Expire
The lease for the  Upper Bluff Road facility expires at the end of June and will not be renewed.   TVA has offered the Outreach Center for use by the CAG for its future meetings.  
Emory River No-Wake  Zone to Be Reduced
Effective  immediately, the no-wake zone on the Emory River has been reduced from Emory  River Mile 1.7 to Emory River Mile 2.9.  The main river channel continues to be  accessible to the public.  For safety, work zones will be marked and boomed  off.  The public will not be allowed in these work zones.   
Ash Consolidation  
Ash consolidation  work being performed at Berkshire is scheduled to be completed by the end of  this month.  However, other work will continue in that area for a number of  weeks.
Next Public  Meeting
We are looking at the  August/September timeframe for the next public meeting where we will report on  the status of the non-time critical work.
If you have any  questions, please give Katie Kline or me a call at  865-717-1645.
Jane  Greenwalt
Project Manager,  Community Outreach  
Tennessee Valley  Authority
Kingston Ash Recovery  Project
Office:   865.717.1645
Cell:   865.806.7688