The Roane County Community Advisory Group (RC CAG) will be holding their first public meeting on December 14th, 2009 @ Roane State Community College.
The meeting will start with a meet and greet with the interim Technical Advisor and CAG members at 6:00 with the meeting starting at 6:30 PM.
The meeting will cover issues with the Engineering Evaluation Cost Analysis (EE/CA) Work Plan and the Community Involvment Plan (CIP). These two documents are out for Public Comment until December 20, 2009.
This is a chance for your voice to be heard.
Saturday, December 12, 2009
Swan Pond Community Press Conference
SWAN POND RESIDENTS PRESS CONFERENCE
THE ONE YEAR ANNIVERSARY OF THE TVA COAL ASH SPILL
The Swan Pond Community residents would like to meet with the members of the press to express the past, present and the future direction they would like to see the Swan Pond Community take. The residents of the Swan Pond Community were the first to be affected by the ash spill on 12/22/08 and continue to be affected to this day.
When: Saturday December 19, 2009
Where: 993 Swan Pond Rd Harriman, TN (behind the Swan Pond Baptist Church)
Time: 2 PM eastern
Background Information: http://en.wikipedia.org/wiki/Kingston_Fossil_Plant_coal_fly_ash_slurry_spill
THE ONE YEAR ANNIVERSARY OF THE TVA COAL ASH SPILL
The Swan Pond Community residents would like to meet with the members of the press to express the past, present and the future direction they would like to see the Swan Pond Community take. The residents of the Swan Pond Community were the first to be affected by the ash spill on 12/22/08 and continue to be affected to this day.
When: Saturday December 19, 2009
Where: 993 Swan Pond Rd Harriman, TN (behind the Swan Pond Baptist Church)
Time: 2 PM eastern
Background Information: http://en.wikipedia.org/wiki/Kingston_Fossil_Plant_coal_fly_ash_slurry_spill
Comments for TDH Public Health Assessment
The PHA (Public Comment Draft) for the Kingston Ash Spill is now available on the web for download.
http://health.state.tn.us/coalashspill.htm
You may submit comments by email at: EEP.Health@tn.gov
Public participation is encouraged please forward to those you feel would be interested. The public comment period will last until February 9, 2010.
Many thanks for your interest and input.
BP
Brad Parman
Environmental Epidemiologist
East TN Regional Health Office
1522 Cherokee Trail
Knoxville, TN 37920
Front Desk: 865-546-9221
Phone: 865-549-5234
Fax: 865-594-5738
http://health.state.tn.us/coalashspill.htm
You may submit comments by email at: EEP.Health@tn.gov
Public participation is encouraged please forward to those you feel would be interested. The public comment period will last until February 9, 2010.
Many thanks for your interest and input.
BP
Brad Parman
Environmental Epidemiologist
East TN Regional Health Office
1522 Cherokee Trail
Knoxville, TN 37920
Front Desk: 865-546-9221
Phone: 865-549-5234
Fax: 865-594-5738
Thursday, December 10, 2009
Dec. 10
Update on Kingston Site Activities
December 10, 2009
New Rail Spurs
New railroad spurs will be installed south of Swan Pond Road and closer to the Kingston Fossil Plant, which will allow the switching to take place away from the road itself. Currently, there are about 25 rail crossings on Swan Pond each day that cause traffic delays for local residents and workers at the Kingston plant and site recovery areas. The new spurs will reduce the temporary blockages on Swan Pond Road. TVA officials studied various options to help alleviate the railroad crossing problems, including building an overpass near the recovery site. The time it would take to construct such an overpass, along with the cost, made that project unfeasible. The new rail spurs are much more cost effective and can be completed by the end of January 2010.
”Curfew” times, in which train crossings are prohibited on Swan Pond Road, will be strictly enforced by the management staff at the recovery site. The current curfew times are:
6:30 – 7:15 a.m.
3:30 – 4:15 p.m.
5:00 – 5:30 p.m.
These times will be reviewed and any changes will be communicated.
Drying Systems
New ash drying systems will be installed at the Site to expedite the removal of fly ash. The benefit to the drying systems is that the sooner moisture can be removed from the stockpiled ash that has been removed from the river, the sooner it can be transported to the Perry County, Alabama, landfill.
The first system to be installed will be a filter press system. A filter press reduces the volume and weight of a slurry waste by separating liquid from the solid. The liquid passes through filter cloths and exits the press leaving behind the filtered solids, called a filter cake. After the desired moisture content is achieved, the press is opened and the filter cake is released.
The second system will be a Genesis Rapid Dewatering System. The system works in stages. First, the ash material passes through a course debris screen, which eliminates and disposes of large objects such as rocks and debris. The next step uses centrifugal force to spin the solids away as the water drains down. Then a computer monitors the changes in the density and flow and injects polymers at various points to produce larger masses of the solids. The rapid dewatering system then captures the fine grain sediments and recovers the water.
Having these new systems will greatly increase our ability to process the fly ash and prepare it for transport to the landfill in Alabama.
Residents in the immediate area as well as plant and site workers can expect a temporary increase in large transport trucks which will be bringing in the filtration and drying equipment, as well as materials to construct the rail spurs. This will begin as early as Friday, December 11 and should last just a few weeks.
Dike C Buttressing Update
Dike C buttressing has begun. Materials needed for this project will come in by truck from the local quarry and from a quarry outside of Roane County. Currently, 46 loads a day will be brought in, half from each quarry. The quarry from outside of Roane County will transport materials in via the interstate and up Swan Pond Road. The local quarry trucks will turn right off of Quarry Road and come onto Swan Pond Road from the North.
Rain Event on December 8
On the day of the high flow event TVA collected a river sample near the Kingston water plant intake. This is in addition to the daily raw water and finished water samples taken by the plant. We contacted the plant operator and he stated he had not noticed any changes in the output from the plant treatment processes.
Excavator
It was pulled out of the river today – there were some delays due to weather and other issues. It will be washed and the plan is to transport it to the south dock for removal on Friday.
Let me know if you have questions.
Katie
Katie Bell Kline
Senior Manager, Community Relations
Tennessee Valley Authority
December 10, 2009
New Rail Spurs
New railroad spurs will be installed south of Swan Pond Road and closer to the Kingston Fossil Plant, which will allow the switching to take place away from the road itself. Currently, there are about 25 rail crossings on Swan Pond each day that cause traffic delays for local residents and workers at the Kingston plant and site recovery areas. The new spurs will reduce the temporary blockages on Swan Pond Road. TVA officials studied various options to help alleviate the railroad crossing problems, including building an overpass near the recovery site. The time it would take to construct such an overpass, along with the cost, made that project unfeasible. The new rail spurs are much more cost effective and can be completed by the end of January 2010.
”Curfew” times, in which train crossings are prohibited on Swan Pond Road, will be strictly enforced by the management staff at the recovery site. The current curfew times are:
6:30 – 7:15 a.m.
3:30 – 4:15 p.m.
5:00 – 5:30 p.m.
These times will be reviewed and any changes will be communicated.
Drying Systems
New ash drying systems will be installed at the Site to expedite the removal of fly ash. The benefit to the drying systems is that the sooner moisture can be removed from the stockpiled ash that has been removed from the river, the sooner it can be transported to the Perry County, Alabama, landfill.
The first system to be installed will be a filter press system. A filter press reduces the volume and weight of a slurry waste by separating liquid from the solid. The liquid passes through filter cloths and exits the press leaving behind the filtered solids, called a filter cake. After the desired moisture content is achieved, the press is opened and the filter cake is released.
The second system will be a Genesis Rapid Dewatering System. The system works in stages. First, the ash material passes through a course debris screen, which eliminates and disposes of large objects such as rocks and debris. The next step uses centrifugal force to spin the solids away as the water drains down. Then a computer monitors the changes in the density and flow and injects polymers at various points to produce larger masses of the solids. The rapid dewatering system then captures the fine grain sediments and recovers the water.
Having these new systems will greatly increase our ability to process the fly ash and prepare it for transport to the landfill in Alabama.
Residents in the immediate area as well as plant and site workers can expect a temporary increase in large transport trucks which will be bringing in the filtration and drying equipment, as well as materials to construct the rail spurs. This will begin as early as Friday, December 11 and should last just a few weeks.
Dike C Buttressing Update
Dike C buttressing has begun. Materials needed for this project will come in by truck from the local quarry and from a quarry outside of Roane County. Currently, 46 loads a day will be brought in, half from each quarry. The quarry from outside of Roane County will transport materials in via the interstate and up Swan Pond Road. The local quarry trucks will turn right off of Quarry Road and come onto Swan Pond Road from the North.
Rain Event on December 8
On the day of the high flow event TVA collected a river sample near the Kingston water plant intake. This is in addition to the daily raw water and finished water samples taken by the plant. We contacted the plant operator and he stated he had not noticed any changes in the output from the plant treatment processes.
Excavator
It was pulled out of the river today – there were some delays due to weather and other issues. It will be washed and the plan is to transport it to the south dock for removal on Friday.
Let me know if you have questions.
Katie
Katie Bell Kline
Senior Manager, Community Relations
Tennessee Valley Authority